Latest News

BANDSTAND WORK BEGINS and other projects

Work began on 1 February 2011 preparing the bandstand base for the
reinstatement of the bandstand.  The preparatory work will take about
two weeks.  Parts of the bandstand are being constructed elsewhere
and will be put into place in a few weeks time.  Improvement of the paths
and landscaping work of the adjacent area will also commence shortly.

Bandstand work commences 1 February 2011

 

 

 

 

 

 

 

 


John Mason (Kirklees Head Gardener in charge of Beaumont Park) and his team
have been working hard to clear the castle site and have created a rockery with
the stone which was removed from the lower pond.  Work has also commenced 
on  the proposed picnic area just off the main drive.  Forestry Department has
removed several trees in the aboretum which were in a poor state and FoBP
woodland management team has continued to cut back vegetation on the
woodland path and above the grottos down Beaumont Park Road.
  Castle site clearance & rockery creation

Picnic area preparation 3 February 2011